The expansion of the marina in Skovshoved was an extensive and interesting project that encompassed tasks such as demolition of existing wharves and piers and dredging of rocks and sand prior to the construction of new piers.

They were built from rock and gravel filler covered by a protective layer of stone slabs.

As part of the expansion, one of the new piers was to cross an existing wastewater pipeline. As the pipeline was older, it could not stand up to the weight of the new pier, and a supportive layer of concrete slabs was required.

We therefore had to dig along both sides, about 2,170 m in all. Using a diver, we then leveled the seabed to install two gravel beds with a tolerance of +/- 3 cm. Then we placed concrete elements weighing up to 18 tons and sheet piles above the existing pipeline.

Det betød, at vi måtte grave langs begge sider, i alt ca. 2*170 meter. Herefter afrettede vi havbunden med anvendelse af dykker, som udførte to parallele skærvepuder med en tolerance på +/- 3 cm. Herefter placerede vi op til 18 ton tunge betonelementer og spunsplader over den eksisterende rørledning.

Overview of the fleet

Comparison of the specifications of our vessels. Contact us at telephone number: +45 75 62 84 11 or email: info@hojmarine.com.

Project information

Project Name
Skovshoved Harbour, Denmark
Project Type Port Construction and Marine Works
Kunde
Arkil A/S
Time Frame
2015-2016
Projektbeskrivelse
Pier construction, boulder and revetment work, demolition, dredging of 80,000 m3.

Benyttede fartøjer