Hanstholm Harbour, Denmark

As part of ongoing maintenance of the water depth, we dredged several basins.

The materials were slightly contaminated and could not be taken to a disposal site at sea. Instead, they were to be placed in a landfill about 2 km from the harbour. This was done by trucks loaded by an excavator at the wharf.

The total volume amounted to 56,000 m³ or 89,600 tons. At 30 tons per truck, that was about 3,000 round trips!

Overview of the fleet

Comparison of the specifications of our vessels. Contact us at telephone number: +45 75 62 84 11 or email: info@hojmarine.com.

Project information

Project Name
Hanstholm Harbour, Denmark
Project Type Port Construction and Marine Works
Kunde
Hanstholm Havn
Time Frame
2015
Projektbeskrivelse
Dredging 56,000 m³ – 1,600 m³ per day transported by truck