Our construction and dredging vessel, Lea Høj, has completed complex channel dredging work at a very shallow port. The dredging work took place over several stretches, as and when funding was approved. Shallow waters required the work to be planned on a daily basis, according to high and low tides. Tides are a constant factor for which the ship’s crew must be able to plan ahead.
Obviously, dredging work can only take place at times when the ship is afloat. This gives the crew two approximately six-hour intervals a day during which the tide is sufficiently high for the complex dredging work to take place. In addition to these tidal conditions, special attention also has to be paid to wind conditions, as easterly winds can force water out of the area with resulting lower high tides and the risk that the ship would be left “stranded” at times when it was supposed to be at work.
The port had attempted other channel-deepening solutions before this contract was commissioned. M/S Lea Høj turned out to be the most effective solution, however, due to its ability to excavate its way through the channel, one small section at a time. The coordinated planning of this project also entailed crew changeovers, which typically took place by jet ski because of the shallow water depth.
This dredging project has not only ensured better access to the harbour. It has also had a positive impact on the local community and on maritime activities in the area.
The construction vessel Lea Høj excavates with an environmental shovel and discharges 110 grammes of CO2 per km excavated.